All Rankings
Most Delayed RERA Projects
Projects with the worst compliance status — highest delivery risk.
| # | Project | Compliance Status | Builder | District | City | Completion | Delayed By | Status |
|---|---|---|---|---|---|---|---|---|
| 1801 |
PMAY OF 116 NO DUS AT VINDHYVASINI WARD DHAMTARI
PCGRERA070622001434
|
Compliant | aayukt nagar palik nigam | Dhamtari | Dhamtari | 2026-09-27 | On track | Ongoing |
| 1802 |
wallfort paradise - 03
PCGRERA071221001301
|
Compliant | jainam builders private limited | Raipur | Raipur | 2026-09-27 | On track | New |
| 1803 |
PMAY FOR 287 NO DUS AT MAHIMA SAGAR WARD DHAMTARI
PCGRERA070622001433
|
Compliant | aayukt nagar palik nigam | Dhamtari | Dhamtari | 2026-09-27 | On track | Ongoing |
| 1804 |
woods estate phase- 05
PCGRERA190122001324
|
Compliant | SRI VENKATESHWARA REALITIES | Raipur | Raipur | 2026-09-28 | On track | New |
| 1805 |
avinash capital homes- ii
PCGRERA180618000227
|
Compliant | SHRI ANAND SINGHANIA, ANAND SINGHANIA | Raipur | Raipur | 2026-09-28 | On track | Ongoing |
| 1806 |
ATAL VIHAR YOJANA PENDRI RAJNANDGAON
PCGRERA061021001276
|
Compliant | E.E. C.G.H.B. Div. rajnandgaon (C.G.) | Rajnandgaon | Rajnandgaon | 2026-09-28 | On track | New |
| 1807 |
shyam city
PCGRERA211021001287
|
Compliant | NANDIKA CONSULTANCY SERVICES PRIVATE LIMITED | Raipur | Raipur | 2026-09-28 | On track | New |
| 1808 |
avinash elegance
PCGRERA241221001307
|
Compliant | AVINASH DEVELOPERS PRIVATE LIMITED, AVINASH DEVELOPERS PVT LTD, AVINASH DEVELOPERS PVT. LTD. THRU-SHRI ANAND SINGHANIA, avinash developers pvt. ltd. | Raipur | Raipur | 2026-09-29 | On track | New |
| 1809 |
deendayal awas yojana kaurinbhata rajnandgaon
PCGRERA061021001275
|
Compliant | E.E. C.G.H.B. Div. rajnandgaon (C.G.) | Rajnandgaon | Rajnandgaon | 2026-09-29 | On track | New |
| 1810 |
GANESHA PARK
PCGRERA210119000896
|
Compliant | tarachand buildtech pvt.ltd. | Raipur | Raipur | 2026-09-29 | On track | New |
| 1811 |
smart city
PCGRERA090519000972
|
Compliant | RATNA BUILDCON THROUGH - KANHAIYA AGRAWAL, RATNA BUILDCON | Mahasamund | Basna | 2026-09-29 | On track | New |
| 1812 |
avinash new town
PCGRERA300120001084
|
Compliant | cosmos developers | Durg | Patan | 2026-09-29 | On track | New |
| 1813 |
shri krishna bhoomi
PCGRERA280919001051
|
Compliant | KANHAIYA AGRAWAL | Mahasamund | Basna | 2026-09-30 | On track | New |
| 1814 |
SAMPOORNA HOMES (PHASE-I)
PCGRERA290319000956
|
Compliant | RAJAT REALTY | Raipur | Raipur | 2026-09-30 | On track | New |
| 1815 |
SAFFRON CORPORATE
PCGRERA270220001098
|
Compliant | esteemed developers and builders private limited | Raipur | Raipur | 2026-09-30 | On track | New |
| 1816 |
VRINDAVAN
PCGRERA040320001102
|
Compliant | RISHABH BUILDTECH INDIA PRIVATE LIMITED, THRU-PRITESH KUMAR JAIN, RISHABH BUILDTECH INDIA PRIVATE LIMITED | Kanker | Kanker | 2026-09-30 | On track | New |
| 1817 |
alaska homes
PCGRERA081119001062
|
Compliant | M/S MAA SHANTI CONSTRUCTIONS BY- ANURAG SHUKLA, M/S MAA SHANTI CONSTRUCTIONS | Bilaspur | Bilaspur | 2026-09-30 | On track | New |
| 1818 |
swarnaa tower and swarnaa business center
PCGRERA310819001032
|
Compliant | PRAGYA BUILDERS | Bastar | Jagdalpur | 2026-09-30 | On track | New |
| 1819 |
GEEKAY TOWNSHIP
PCGRERA060219000908
|
Compliant | GEEKAY DEVELOPERS THROUGH - SURESH ATLANI, GEEKAY COLONIZER & BUILDERS LIMITED, DIRECTOR-SHRI SURESH ATLANI AND SHRI ABHISHEK ATLANI, (01) GEEKAY DEVELOPERS, THROUGH- SHRI ABHISHEK ATLANI, (02) SHRI VIVEK KHANDELWAL, GEEKAY DEVELOPERS | Raipur | Raipur | 2026-09-30 | On track | Ongoing |
| 1820 |
NARAYANI INCITY
PCGRERA280319000950
|
Compliant | SARVAMANGLA BUILDCON | Korba | Korba | 2026-09-30 | On track | Ongoing |
| 1821 |
sampoorna homes phase-II
PCGRERA120419000961
|
Compliant | RAJAT REALTY | Raipur | Raipur | 2026-09-30 | On track | New |
| 1822 |
v.v.d. city
PCGRERA260220001095
|
Compliant | vijay kumar duggar | Raipur | Raipur | 2026-09-30 | On track | New |
| 1823 |
narayani vihar
PCGRERA250419000963
|
Compliant | SARVAMANGLA BUILDCON | Korba | Kartala | 2026-09-30 | On track | Ongoing |
| 1824 |
high park phase- i
PCGRERA100619000978
|
Compliant | H.R.DEVELOPERS | Raipur | Raipur | 2026-09-30 | On track | New |
| 1825 |
SHREE KRISHNA VIHAR PHASE -II
PCGRERA131118000840
|
Compliant | Shree krishna developers | Bemetara | Bemetara | 2026-09-30 | On track | New |